Buying a Custom Automated Assembly Line from China: Specification, Line Balancing, Traceability, Quotes, TCO and Acceptance Testing
By Longen Automation (Jiangxi Longen Automation Equipment Co., Ltd.) – custom automation, assembly line and robot system manufacturer since 2012, Yichun, China.
Short answer: Most delays and cost overruns on custom automation come from incomplete requirements at the start and unclear acceptance criteria at the end. Give the supplier complete technical information, insist on a line-balance and cycle-time study, understand exactly what the quotation includes, calculate total cost of ownership rather than purchase price, verify the integrator's real project evidence, and agree written FAT and SAT criteria before signing.
1. What technical information should buyers give an automation line manufacturer?
- Product data: 3D models and 2D drawings of every part and the finished product, with tolerances, materials and weights; physical samples if possible.
- Process: the assembly or production sequence, each operation's quality requirements, and a video of the current manual process.
- Output: required output per hour, shift pattern, number of product variants and how often you change between them.
- Factory: floor plan with available space, ceiling height, columns, doors, power supply (voltage, frequency), compressed air and network.
- Interfaces: upstream and downstream machines, MES/ERP connection needs, labelling and data requirements.
- Standards: destination country, required certifications (for example CE for the EU), safety and electrical standards, preferred component brands (PLC, robot, pneumatics).
- Acceptance: how the line will be tested and accepted (see section 8).
Incomplete information is the main cause of design changes; a written User Requirement Specification (URS) avoids most of them.
2. How do you balance manual, robotic and inspection stations to find bottlenecks?
- Takt time = available production time ÷ required output. Example: 7.5 h × 3600 s = 27,000 s; for 1,000 units, takt = 27 s.
- List every work element with its time (time study for manual work, simulation or supplier data for robots and machines) and its precedence (what must happen before it).
- Minimum number of stations = total work content ÷ takt (rounded up).
- Assign elements to stations so that no station exceeds takt, respecting precedence.
- Line efficiency = total work content ÷ (number of stations × longest station time). The station with the longest time is the bottleneck.
- Improve the bottleneck: split its work, add a parallel station, automate it, or add a buffer in front of it. Robots and inspection machines often have fixed cycle times, so build the balance around them.
3. How does an assembly line support quick changeover and error-proofing for mixed models?
- Product identification at the start of the line (barcode, QR or RFID on the part or pallet) so every station knows which model it is building.
- Recipe management: the PLC or MES downloads the right parameters (torque, press force, test limits, robot program) for each model automatically.
- Quick-change tooling: universal pallets or quick-release fixtures; tool changers on robots.
- Error-proofing (poka-yoke): pick-to-light, part-presence sensors, vision checks, torque and angle monitoring on screwdrivers, and interlocks that stop a pallet leaving a station until the step is confirmed OK.
- Changeover target: measure the current changeover time and set a target; move as much work as possible to while the line is still running.
4. How can an assembly line use barcodes, RFID, PLCs and MES for product traceability?
- Give every product an identity at the first station: a laser-marked or labelled serial number, or an RFID tag on the pallet linked to the product serial.
- Read it at each station, so the PLC knows which unit is present.
- Record process data per serial number: components and batch numbers, torque and angle curves, press-fit force, test results, operator, time.
- Send data to MES (or a line database) through an agreed interface such as OPC UA or a database link.
- Block bad parts: a unit that failed a step cannot pass the next station until it is repaired and re-tested.
- Plan for failures: a manual data-entry and re-label procedure when a tag cannot be read.
5. What costs are normally in a custom automation quotation, and how are changes priced?
A complete quotation should list:
- Mechanical, electrical and software design
- Equipment and components (with main brands named)
- Fixtures, pallets and grippers
- Manufacturing, assembly and factory acceptance test (FAT)
- Packing, transport terms (for example FOB or CIF), insurance
- Installation, commissioning, site acceptance test (SAT) and training – including who pays for engineers' travel and accommodation
- Documentation (manuals, drawings, spare parts list)
- Warranty and recommended spare parts
Ask what is excluded: foundations, utilities, network, local certification fees, import duties and customs.
Engineering changes: agree a written change procedure. Every change after design freeze is assessed for cost and delivery impact and approved in writing before work starts. Changes are usually priced on engineering hours plus material, and late changes cost more than early ones.
Longen's typical terms, for reference: engineering review within 1–3 days, solution and quotation in 3–7 days, payment 30 % deposit, 60 % before shipment and 10 % after acceptance, by T/T or L/C.
6. How do you calculate total cost of ownership and payback for an automated line?
Total cost of ownership (TCO) over the expected life (often 8–10 years):
- Initial investment: equipment, shipping, duties, installation, training
- Running costs: energy, compressed air, consumables
- Maintenance: preventive maintenance labour, spare parts, service contracts
- Downtime: lost output during breakdowns and changeovers
- People: operators and technicians still required
- End of life: residual value or disposal
Simple payback (years) = initial investment ÷ annual net savings, where annual net savings = labour cost saved + quality savings (less scrap and rework) + extra output value − running and maintenance costs.
Illustration only – not a price or a guaranteed saving: an investment of USD 300,000 that saves 6 operators per shift on two shifts (12 people × USD 12,000 per year = USD 144,000) and costs USD 24,000 per year to run and maintain gives net savings of USD 120,000 and a payback of 2.5 years. Replace these figures with your own labour cost, shifts and output.
7. What should buyers check when choosing an industrial robot system integrator?
- Comparable projects: similar product, process and output; ask for videos of running lines and customer references you can contact.
- In-house engineering: mechanical, electrical, PLC and robot programming engineers, and how many are assigned to your project.
- Manufacturing capability: own factory, machining and assembly, and space to build and run your line before shipment.
- Quality system: ISO 9001 certification and a written FAT procedure.
- Safety and compliance: experience with your country's requirements (for example CE marking documentation for the EU).
- Project management: a named project manager, schedule with milestones, and weekly progress reports with photos.
- After-sales: remote support, spare parts stock, response time, and on-site service options in your region.
8. What should be inspected in factory acceptance testing (FAT) and site acceptance testing (SAT)?
FAT (at the supplier's factory, before shipment):
- Visual and dimensional check against the approved layout and specification
- Component brands and models as quoted
- Every station and function in manual and automatic mode
- Cycle time and output over a continuous run (for example 2–4 hours) with real parts
- Quality results: first-pass yield, measurements, test results
- Changeover between models
- Safety functions: e-stops, guard interlocks, light curtains, reset logic
- Alarms, HMI screens, data recording and traceability
- Documentation draft: manuals, electrical drawings, spare parts list
SAT (at your factory, after installation): repeat the key tests with your utilities, materials and operators, then run a longer production test (for example several shifts or days) to confirm output, availability and quality. Sign off with a punch list of open items and dates.
Agree the FAT and SAT criteria in the contract, linked to payment milestones.
How Longen Automation can help
Longen designs and builds custom automated assembly lines, BORUNTE robot cells, coating lines and conveyor systems, with headquarters and factory in Wanzai County, Yichun (Jiangxi), a subsidiary, Wenling Longen Automation Equipment Co., Ltd., in Luqiao, Taizhou (Zhejiang), and 40 R&D engineers. Every line is built and tested in our factory before shipment, installation and operator training are included, and equipment repairs are free of charge within the first year. Our equipment is installed in South Korea, Indonesia, Vietnam and Egypt, and we export by sea from Shenzhen, Ningbo and Shanghai.
Send your product drawings, output target and factory layout for a free engineering review within 1–3 days: WhatsApp / phone +86 133 2005 6136, email Sales001@lezdh.com.